TRUMPF Production Building Schramberg

As part of the master plan for the Trumpf Laser Schramberg company campus, the new production building was developed as an extension of the existing laser factory (built in 2000). Its appearance and materiality take up the language of the existing buildings and develop it further.

The 12,000 square meter new building, with two upper floors and a basement, houses production areas with clean rooms, assembly and office areas, the central goods-receiving-department and an energy center for the entire campus. Due to the steeply sloping terrain, the south side of the basement is fully lit: the new building presents itself here to the outside world as a three-story building.

The open and transparent aluminum-glass facade is vertically structured by aluminum fins, which are 50 cm deep and are mounted at a distance of 1.50 m. Between them is an external sun protection. The rough aesthetics of the exposed concrete walls and the black steel- railings, doors and window frames inside the building contrast with the exterior appearance. The development core, which is located around the vegetated inner courtyard, indicates the clear, open and transparent structure of the building.

While the axial dimension of the columns on the lower two floors is 7.50 m x 7.50 m, horizontal precast concrete beams with a length of 22.5 m form the roof frame on the upper hall floor and ensure column-free assembly halls. Here, the production areas and clean rooms are arranged according to a box-in-a-box principle. The working areas are naturally lit both through the outer facade and partly through the courtyard facade: this accords the employees a wide view of the greenery and creates a pleasant working atmosphere. The surrounding external visitor corridor between the façade and the clean rooms also provides views of the work areas.

Project Information

Architects 

Barkow Leibinger, Berlin

Frank Barkow, Regine Leibinger

 

Team
Klaus Reintjes (Associate, Project Architect), Jonas Altorfer, Ana Filipovic, Nicolai Jasper, Michael Maier, Christina Möller, Elizaveta Mosina

  

Program
Production halls with clean rooms, office spaces, supply and break room 

 

Location

Schramberg, Germany 

 

Size

12,100 sq m | 130,361 sq ft

 

Construcion

05/2016  – 12/2017 

 

Photos

© David Franck 

 

 

Client

TRUMPF Laser GmbH

 

Tendering/Construction Management 

Gassmann + Grossmann Baumanagement GmbH, Stuttgart

 

Structural Engineering 

Breinlinger Ingenieure, Tuttlingen 

 

Climate/Energy Design

Transsolar Energietechnik GmbH, Stuttgart


Façade Consultant

MBS Projekt GmbH, Wietze


Landscape Architect 

capattistaubach Landschaftsarchitekten, Berlin

 

MEP Engineers, Mechanical Engineer

Krebs Ingenieure GmbH, Ditzingen 

 

Electrical Engineering

Müller + Bleher Filderstadt GmbH Co.KG, Filderstadt

 

Building Physics 

Ingenieurbüro für Bauphysik Horstmann + Berger, Altensteig

 

Underground Construction, Traffic

Breinlinger Ingenieure, Tuttlingen